Crucial milestone for Skandia Gateway

The Skandia Gateway project in Gothenburg has reached a crucial milestone. The environmental impact assessment has been completed, and documents have been submitted for examination by the Land and Environment Court.

Initial studies were conducted in 2014-2017 to address the need for more extensive dredging of the fairways and the inner port area. The studies were part of a provisional plan to increase capacity at the Skandia Terminal and enhance the competitiveness of the only port in Sweden with direct services to the Far East. The lead time for an infrastructure project of this nature and magnitude is 8-10 years.

The Swedish Maritime Administration and the Gothenburg Port Authority have now submitted permit applications and an environmental impact assessment, consisting of more 1,000 pages, to the Land and Environment Court in Vänersborg. The assessment is a collective evaluation of the project’s impact on human health and the environment.

A permit from the Land and Environment Court is vital if quay reinforcement at the Skandia Terminal is to commence in 2022, and dredging in 2024, and if work to increase quay depth is to be completed by 2026. The permit review will not only cover quay reinforcement but also water-based work, including blasting and dredging in the Northern Fairway, previously the Torshamn Fairway, and in the dock at the Skandia Terminal. The hope is that negotiations with the Land and Environment Court can commence during the latter half of 2021.

Ships have grown in size over the years, and deeper fairways are essential. The most efficient section of the fairway has been identified by pilots from the Gothenburg pilot area with the aid of the Maritime Administration simulator. Some 60 test runs were undertaken in varying weather and wind conditions and using a virtual vessel measuring 430 × 65 metres and with a draft of 17.5 metres. The simulations were also used to determine dredging volumes.

The Transport Administration forecast for 2040 shows that 65-70 per cent of Swedish container volumes to and from the Far East will pass through the Port of Gothenburg. A socioeconomic analysis reveals that direct shipping results in a lower transport cost, reduced transport time, and lower environmental impact per unit.

Positive
The Safer Fairways dredging project in Gothenburg commenced back at the beginning of the 2000s. The Skandia Gateway project will focus on the same type of work, to a similar extent, and in the same areas.

“The Safer Fairways follow-up has revealed that no permanent negative environmental consequences arose during or after dredging. Skandia Gateway will in many ways be a repeat of Safer Fairways. The main difference now is that ships are a couple of sizes bigger,” said Patrik Benrick, Skandia Gateway Project Leader at the Swedish Maritime Administration.

“Submission of documentation to the Land and Environment Court is a crucial milestone if we are to achieve our common project goals and with completion during the first half of 2026 at the latest. It is encouraging to see the progress we have made,” said Jan Andersson, Skandia Gateway Project Manager at the Gothenburg Port Authority.

Skandia Gateway is a joint project run by the Gothenburg Port Authority, the Swedish Maritime Administration, and the Swedish Transport Administration.

Topics


Fact file: Port of Gothenburg
The Port of Gothenburg is the largest port in the Nordic region. 30 per cent of Swedish foreign trade passes through the Port of Gothenburg as well as half of all container traffic.

The Port of Gothenburg is the only port in Sweden with the capacity to receive the world's largest container vessels and has the broadest range of shipping routes within and outside Europe. The 25 rail shuttles that depart each day mean that companies throughout Sweden and Norway have a direct, environmentally smart link to the largest port in the Nordic region. The Port of Gothenburg has terminals for oil, cars, ro-ro, containers and passengers.

www.portofgothenburg.com

Follow us on Twitter

Contacts

Press Officer on call

Press Officer on call

Press contact 24/7 media hotline +46 31 368 75 70
Stefan Strömberg

Stefan Strömberg

Press contact Press Officer +46 31 368 77 15
Media Content Panel
Skandia Gateway layout
Skandia Gateway layout
License:
Media Use
File format:
.jpg
Size:
5906 x 1624, 1.54 MB
Download
Media Content Panel
Flygbild Göteborgs Hamn
Flygbild Göteborgs Hamn
License:
Creative Commons Attribution
File format:
.jpg
Size:
3809 x 2539, 7.18 MB
Download

Related content

The film "Skandia Gateway" shows how the project will make it possible for the world's largest ship to enter the Port of Gothenburg fully loaded and provide increased efficiency and less climate footprint.

Construction of Skandia Gateway proceeding according to plan

The Skandia Gateway project is already under way and construction is scheduled to begin during the first quarter of next year 2022. The fairway needs to be deepened to 17.5 metres if the world’s largest ocean-going vessels are to be able to call at the Port of Gothenburg fully loaded. This will prove crucial if Swedish industry is to have greater access to the world in the future.

The Port of Gothenburg is the only port in Sweden that can receive the world’s largest vessels. At present they are unable to do so fully loaded. Therefore, the fairway needs to be deepened and quays strengthened.

Decision for a deeper fairway in the Port of Gothenburg

The Land and Environmental Court granted a permit for deepening and widening the fairway, strengthening the quay and the disposal of dredge spoil in a designated location at sea. The decision will allow the Skandia Gateway project’s dock reinforcement work to start according to schedule.